Yanbu II - Project Update

On the 14th of January at 3pm local time, Shanahan Engineering achieved a major milestone for customer Hanwha Engineering & Construction - the first firing of the auxiliary boiler at the Yanbu II project in Middle East.

This signals the first success for the 80 strong Shanahan Engineering team which is working on the Oil fired power station and desalination project in Yanbu Industrial City.

The firing of the boiler involved a huge team effort to bring fuel on site and transfer fuel to achieve the final success.

The on-site SEL commissioning team consists of those developing the program (procedure preparation), to the operations team down, to the team performing the system walk downs / TOC package reviews.

Tae Lim of Hanwha E&C said; “There is not enough that could be said to express the appreciation for all the hard working people who made this possible.”

Shanahan Engineering was awarded the commissioning contract early last year by Hanwha E&C to carry out the start-up work as part of their EPC contract.

Below pictures of the Auxiliary Boiler first fire and  "building a project as a team" Shanahan Engineering and Hanwha weekly football game

Auxiliary Boiler First Fire ,  Auxiliary Boiler Initial Flame

Aux Boiler first fire 14 Jan 15 3

  Aix boiler ititial flame 2

 

 

 

 

 

 

 

 

 

 

 

  

  Football Team Yanbu

News

  • Completion of steam turbine reliability test at PP14 Power P…... > Read more

  • Shanahan Successfully achieves Full Speed No Load milestone... > Read more

  • Shanahan Engineering reveal refreshed branding to align with…... > Read more

  • Shanahan Engineering announce the appointment of Kevin McCar…... > Read more